From The City And County Of Honolulu
Excavation of the Kaneohe
– Kailua Gravity Sewer Tunnel is almost complete. In order to maximize the
efficiency of this work, the contractor, Southland / Mole JV (SMJV), will be
commencing a second work shift allowed per the project noise variance approved
by the Department of Health. The noise variance allows work within the Kaneohe
Wastewater Pre-treatment Facility (WPTF) 24 hours/day, except Sundays.
The second shift SMJV is planning to work at the Kaneohe WPTF
will be from 5:30pm to 4:30am, Monday thru Friday and Saturday from 5:30pm
until Sunday morning at 12:00am starting Monday, June 6, 2016.
Work will be restricted to be within the Kaneohe Wastewater
Pre-treatment Facility and will be focused near the tunnel entry/exit shaft
away from residences. Work will include removal of the Tunnel Boring Machine
(TBM) that excavated most of the 3-mile-long tunnel, and installation of
10-foot final tunnel lining pipes. Deliveries to the site and backup alarms
will be restricted to the permit daytime hours only. There will be no
deliveries to/from the site during the nighttime variance hours.
If you have any questions about this update or the project,
please feel free to contact the Construction Management Team.
Project Hotline: (808) 445-9079
Email: info@kktunnel.net
Email: info@kktunnel.net
Mahalo for your patience and understanding.